The City held its first public open house on Jan 27, 2015 to present and solicit feedback on its proposal to widen the airport parkway. This project is
proposed to have a 3 stage rollout as follows:
Stage 1: expand
Airport parkway to 4 lanes divided hwy between Hunt Club and
Brookfield
- Completion is
envisioned for 2019, Projected Cost: 31m$
Stage 2: expand
Lester Rd to 4 lanes between Albion Rd and the Airport
Parkway
- Completion
envisioned for 2020-2025 timeframe, Projected Cost: 13m$
Stage 3: expand
Airport parkway to 4 lanes divided hwy between the Airport and Hunt
Club
- Completion
envisioned for 2026-2031 timeframe, projected cost 36m$
End-End project cost
= 80m$
The study is
expected to go through 3 rounds of public open houses and be finished in the latter half of 2016. More details...Airport Parkway Widening: Details |